Click Here for a Video of SRP Horse Mesa-Dam
Video Clip
If you are unable to play the video, click here to download the
software
Windows
Media Player
|
|
 |
|
|
 |
|
|
 |
|
|
 |
Site
Preparation (better named "logistics")
The dam site, being 300 feet above the river below, surrounded
by rock cliffs and more than and hour and a half from civilization
created challenges to even getting to the site. The only dry access
to the site is a 20-minute mountain trail which traverses back
and forth through a steep canyon in the one of the most rugged,
arid and rocky environments in Arizona. Regular semis refused
to travel the road, requiring all deliveries of equipment, scaffolding
and material to be brought in on smaller flat bed trucks. An old
school house, from the original construction campground 60 years
ago, was renovated to house the on-site cook, food supplies and
four team members. Four camping trailers were acquired (room for
only four) to house an additional 16 of the 24 men required to
man the project. The remaining 4 men roomed at the marina motel,
accessible only by boat from the site. Accessing the work areas
safely required building scaffolding in areas only accessible
by professional rigging crews. Rhino, the subcontractor selected
for rigging, was able to utilize rappel lines with all of the
appropriate fall protection, to gain access and install the initial
leg supports on the rock cliffs and old concrete spillway below
the work area. Action Scaffolding was selected to provide and
erect the system scaffold around each pier, to include stair towers,
staging and debris netting. Although site is actually a power
generation station on a river, there was not adequate power or
water for use in construction. Generators were used to make the
appropriate 240 3 phase power. The lake water was determined to
have too many chlorides for use in anything other than the 7 day
wet cure. Potable water was brought in via water wagon from the
spring location a few miles away.
Demolition Method
Removal of deteriorated concrete included a few surface repairs
only an inch or two deep and mostly larger repairs from six inches
up to a foot deep. The concern that large pneumatic hammers might
cause undue stress and vibration through the remaining structure,
creating additional damage, was the initial reason for restricting
demo hammers to less than 90# hammers. The demolition process
was therefore performed by hand using smaller pneumatic chipping
hammers. To address the large amount of compressed air that would
be needed and the inability to locate large equipment near the
site, a 1000 cfm air compressor was staged at the road. The air
was piped to the site where it was allocated to the various tools
with a custom-fabricated, high-pressure manifold. The debris fell
to the various levels of scaffolding, where it was collected and
placed into buckets and lowered down the 800 foot cable stretched
across the river, from the spillway to the road below. The debris
bucket emptied directly into the dump trailer for disposal. To
achieve the desired removal of concrete behind existing reinforcing
steel, chipping hammers and bush hammers were utilized.
Surface
Preparation
After the demolition was completed, the host concrete and the
steel were sandblasted. To thwart off any new ASR, perhaps regenerated
by the application of new materials, the surface of the repair
areas were treated with the lithium nitrate prior to placing any
material. Following the specification and manufactures' recommendation,
the substrate was saturated surface dry (SSD) using potable water,
prior to material application.
Application
Method Selection
Various methods of placing material were evaluated including:
form and pour, wet process shotcrete, and dry process shotcrete.
Dry process shotcrete was determined to be the most efficient,
cost effective method while being able to deliver quality repairs.
The shotcrete pump (dry process gun) would have to be located
on the top of the dam, while the repairs were being shot 200 feet
away and 75 feet below the top of the dam. Wet process would have
required slower set materials and a clean-out area. A clean-out
area was feasible but the wet process method would never allow
for temporary shut-downs due to mobilizing to new areas or even
lunch breaks. Forms would not have allowed for the thorough inspection
of surface prep, the timely application of protective coatings
on the steel nor the consistent application of the lithium. Dry
process shotcrete allowed for temporary shut downs of the gun,
just-in-time ordering of full truckloads of bagged materials (over
10,000 bags used), reduced the waste from clean-out, and allowed
for visual ongoing inspection of the repairs as they was being
placed. Air pockets, voids and honeycombs were non-existent. Bagged
materials were able to be delivered in full pallets to the gun
location on the top of the dam. The addition of lithium to the
dry bagged goods was performed at the mix station just prior to
placing the material in the gun hopper.
Repair
Process Execution
Although the bulk of the work was dry-process shotcrete, other
repair methods were incorporated as required. Epoxy injection
of crack repair was performed to over a half mile of cracks including
removal of surface sealer. Urethane foam injection was performed
on all moving joints to prevent moisture intrusion. Due to the
30 feet of head pressure behind the dam, urethane foam injection
was also used to stop the seeping of water onto the spillway and
into the repair areas. The control joints on the spillway were
all cleaned and caulked with reservoir grade urethane sealant.
Deteriorated reinforcing steel (square bar) was removed and replaced
as needed. Once the repairs were completed on the top of the spillway,
the entire surface was treated with the topical version of the
lithium and portions of the slabs were then sealed with an epoxy
flood coat. For aesthetics and safety reasons, the epoxy flood
coat was seeded with sand. Unforeseen conditions found During
the repair process, certain locations were deemed to be unsafe
due to the hazard of rocks falling. The size of the rocks were
sufficient to crush a large truck. (Or the powerhouse below) Repairs
needed to be done, however, and the contractor was requested to
install the appropriately engineered rock netting and rock anchors.
This occurred more than once, each time with successful results
from the remedial work.
Special
features
The project required approximately 24 men full-time for nine months
in the extreme Arizona environment, working 300 feet above the
river using rappel lines and lifelines constantly. During the
entire project there were no lost-time accidents or injuries resulting
from the work at this site. This is truly a safety accomplishment!
Back
to Main Page